Why does my budgeted cost change every time I recalculate the schedule
In the Open Standard
Tom TomMember for 12 years 2 months
- Created
- 3
- 4
0
I just created a cost loaded schedule and everything look fine. The problem is that everytime and re-run the schedule the budgeted cost changes on me and it driving me crazy. This only happen on a particular resource. P6 always always add or subtract some decimal points to whatever I input. For example, $350,000 would change to $349,999.78. What is going on?
3 replies