Issue Exporting Version 15 to Microsoft Project

William ManleyMember for 10 years 5 months
Created
2
2
0

Dear Primavera wizards,

I am having an issue exporting version 15 to Microsoft Project.  Normally, in previous versions, I seem to recall exporting to .mpp files.  This version only gives me the option of .xml's (2010, 2007, 2002/2003) and MPX.  This is a function I have performed many many times in older versions, but seem to be having an issues here.  Any help here would be greatly appreciated.

 

Regards,

Bill

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi William,it's amazing that

    Hi William,

    it's amazing that Primavera is reconning the MPX format, ignored by MS Project since MSP 2K; maybe Microsoft does not want once again to give the necessary code to Oracle, or Oracle is considering the MPP format not reliable

    Using the XML format is really easy and productive 

    Alexandre

  2. 0
    Richard Wall ·

    I've just received a message

    I've just received a message from Oracle about exporting to MSP using 16.1. They said 16.1 has a bug in it and they will need to come out with a patch for 16.1 to export to MSP. They also said, that 15.2 works fine and will export to MSP using the .XML format.

     

    Also, make sure you have create the JAVA_HOME in the Enviramental Variables on your computer. You will need the JAVA JRE installed. It will a path similiar to C:\Programs Files\Java\jre<version>. Create JAVA_HOME and then copy and past the Java string into the Enviramental Variables.....click ok, ok, ok