Check Schedule in P6 Web

Dieter WambachMember for 19 years 9 months
Created
2
2
0

Hello

I have an issue with the function Check Schedule. It does work for projects up to 1500 activities but not if there are more activities.

Is there any setting within the web server which limits the size of a file? Do you know any other reason?

I'm using Waterfox as a browser; colleagues who use the internet explorer experience similar.

We have P6.8.3.

 

Thank you very much and best regards

Dieter

2 replies

Oldest first
  1. 0
    Anujkumar Mishra ·

    Hello All, I am also facing

    Hello All,

     

    I am also facing the same issue with Primavera Ver 8. I am using Web based option to Check Schedule. However Result indicate "None Found",

    This is happening for one particular project. For other project, I am able to check schedule. 

    I don’t know the reason, why I am unable to check schedule for the Particular Project.

     

     

     

    Regards,
    Anuj

  2. 0
    Anujkumar Mishra ·

    aedit

Log in or join to reply