Unable to configure P6 EPPM database with P6 Client.

Maddy JaisMember for 11 years 7 months
Created
1
23
0

Hi,

 

Can you please explain how to configure P6 EPPM database schema with P6 client as im not able to configure same db instance in P6 client.Its saying you cant configure EEPM database in P6 Professional.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    go to 'All Programs'' -->

    go to 'All Programs'' --> 'Microsoft SQL Server' --> 'Configuration Tools' --> 'SQL Server Configuration Manager'
    SQL Server Config Mngr window will open.

    In the right hand site of the window you will see different data bases. Right Click on the SQL Server 'Primavera' and click 'start'.
    Then try again to log in in Primavera

Log in or join to reply