Primavera Resource Management
- Created
- 7
- 1
Good day all.
For many years now I have tried to get a very specific answer to a resource and cost related issue with Primavera from all kinds of industry experts, training experts and Oracle themselves, all to no avail.
To pain the picture, what would be ideal is that activities could carry detailed resources of all types with their associated costs and have no relevance to a performance or productivity assumption, as we all know, the assumption will very rarely be what actualizes.
Simple example.
Activity - Build Steel Structure
Steel structure has a BOQ of 1000 tonnes of steel, at say $10 per tonne (material resource)
We can assume we need a crane at say $50 per hour (non-labor resource)
1 steel erector at say $5 per hour (labor resource)
1 supervisor at say $15 per hour (labor resource)
Assuming this estimate duration is 20 days, we create the activity (task/resource dependent) with the resources above assigned to them with their relevant costs and quantities
| UoM | Qty | Rate | Days | |||
| Steel | Material | tonnes | 1000 | $ 10.00 | n/a | $ 10,000.00 |
| Steel Erector | Labor | per hour | 1 | $ 5.00 | 20 | $ 800.00 |
| Supervisor | Labor | per hour | 1 | $ 15.00 | 20 | $ 2,400.00 |
| Crane | Non-Labor | per hour | 1 | $ 50.00 | 20 | $ 8,000.00 |
| $ 21,200.00 |
So assumptions on costs as above.. Activity is loaded with these 4 resources.
Steel is fixed as it is a fixed quantity to install, but the labor and non-labor resources are based on how long they will work, as their cost is time related.. So it all goes well and the 20 days is achieved, it will cost as above, but if after day 5 we are slipping, there is no way for Primavera to give us an accurate forecast of cost to complete for that activity.
Please don't get me wrong, as it can be done manually, and for each resource you would have to calculate the remaining duration based on productivity to date and can capture that it, but what is the use therefore of resource loading with costs your schedule?
This is a major frustration for some years now, any work arounds to this would be greatly appreciated, as one can imagine, a construction schedule with numerous thousands of activities in gets very tedious to update if you are needing to do so many external calculations just to update the P6 schedule correctly.
I hope I have clearly expressed the issue and look forward to some responses..
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?