is this a new airport or a renovation of an existing airport ?
is there road work ramp work enplaning and deplaning ? do you have to keep these active during construction ?
is there a phasing plan ?
how many gates can you take down at a time ?
are you building any additinal runways ?
do you need swing spaces for exisrting tenenats ?
are you building a additinonal fuel tank farm ?
are you installing a gylcol recovery system ?
are you building a de-icing area ?
are you installing in ground fuel tanks at the gates ?
is there taxiway work ?
is there runway work ?
is there loading dock work ?
is there air traffiic control tower wok as well as ground control tower work ?
how long does it take for construction personell to go through the badging progess to get AOA access ?
how are you going to get the craft onto the AOA area ? bus ?
are there seperate gates for the craft as opposed to airport employees ?
are you bringing in concrete or do you have an onsite batch plant ?
do you have a deciated haul road through the airport as well as a stock pile area ?
are you working in an international arrivals area if so do your people need to be finger printed ?
shall I go on ?