Baseline Resources - reports
- Created
- 2
- 3
Good afternoon all,
I've been asked if I can generate a report from P6 to show our current plan resource amount vs our baseline resource amount.
i.e. when we baselined a job we had for example 20 tons of steel used, as the project has progressed this has changed a few times and I want to be able to get out of the P6 baseline what our original figure was so we can see how far it has changed in the time between.
I'm fairly sure that without detaching the baseline and going into it manually the above report can be done. My line manager is convinced P6 allows this.
Can someone give us a defintive answer? if I'm wrong then great can you tell me how to do this, if I'm right and it needs detaching then someone else has some work to do :)
thanks
Thom