Performance % and Schedule % Complete not being displayed in Cost Loaded Program at WBS Level

Prateek SinghMember for 10 years 8 months
Created
1
2
0

Please help!!

In my cost loaded program the Performance and Schedule % complete are showing as 0% at all WBS Levels but budgeted and actual costs are displayed.

Morever, when i further collapse the program to the activity level, the performance % complete is being shown but the schedule % complete is still being displayed as 0% for the activity.

 

Please explain how to track the schedule and performance % complete at WBS level too.

 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    you can not roll this up at

    you can not roll this up at wbs level this is by design becasue there are 3 different types of % complete that you can choose whoch are "Duration", "Units", or "Physical. So if some activites were duration % complete and some were units % complete and some were physical % compelte then you would have apples,, oranges & pears. 

    If you want to use WBS Level % Complete then you can use steps

    The percent complete using the WBS Milestones that are assigned to a WBS level. Computed as Actual Weight of Completed Milestones divided by the Total Possible Weight of All Milestones. 