Notification flags

Nick JacksonMember for 19 years 3 months
Created
3
2
0

I'd like to create a schedule of dates that move with the programme for notification periods flagging when to submit documentation. Example would be a method statement that needs submitting 20 days before the planned date that work starts. As the the programme moves with progress I want the submission date to move as well, but I don't want to clutter the programme as there will be many docs to submit at various times.

 

I don't want to use ALAP constraints with lags as they degrade the programme score, so I'm hoping P6 has a tool to generate this schedule elsewhere.

 

Alternative I guess is to export to Excel and manage it there, but I'd prefer not to do that as its extra steps where things can go wrong in translation.

 

Any ideas?

3 replies

Oldest first
  1. 0
    Rafael Davila ·

    I do not use P6 but maybe you

    I do not use P6 but maybe you can try using a few User Defined Fields [UDF] along with a Global Change ...

      UDF1UDF2UDF3
    StartFinishNotification_TypeNotification_LagNotification_Date
        To be updated using Global Change
      S/F/emptyX(days)IF(Notification_Type ="S",Start-Notification_Lag,IF(Notification_Type ="F",Finish-Notification_Lag, ""))

    You will have to figure it out the details on the global change formula.  Maybe P6 provides for UDF data validation and you can define it to be as per a pull down menu.

    If it works as expected then you can filter Notification_Date by any date range.

    Good luck

  2. 0
    Nick Jackson ·

    Hmm that's an idea, I'll give

    Hmm that's an idea, I'll give it a go thanks

  3. 0
    Rafael Davila ·

    I gave it a try using my

    I gave it a try using my software of choice and it worked as expected. The notification type is selected from a pull down of 3 values (empty/S/F) and the formula is applied automatically as specified, whenever a schedule run is executed.

    Notifications01 photo Notifications01_zpsf9zesppc.jpg

    Notifications03 photo Notifications03_zps31wtll4e.jpg

    Notifications04 photo Notifications04_zpsvacoydkh.jpg

    The formula is a bit tricky as I had to convert B into seconds, this you shall figure out.

    Notifications02 photo Notifications02_zpspiqwntrp.jpg

    Good Luck