planning units
In the Open Standard
Abeer MohamedMember for 9 years 10 months
- Created
- 4
- 1
0
dear all,
i created resource excavation budget is 22965 m3 at the beginning of the project & this budget by p6 divided as follows aug. 21872, at Oct. 608 & Nov. 216.
which is not appropriate for the project so i need to adjust it manual per month on P6 as follows:
aug. 10188, at Oct. 7139 & Nov. 5368.
please clarify how can i do it in steps especially the project is active and now i prepared the updated till end of Nov.
regards.
4 replies
Oldest firstLog in or join to reply