Calendar for scheduling Relationships Lag

Luis GarridoMember for 9 years 9 months
Created
6
1
0

Hi,

I have the following issue regarding how Primavera calculates lag between activities depending on the "Calendar for scheduling Relationships Lag":

 

I have inherited a programme that has been set to calculate lag with the 24 Hours Calendar. That programme uses 3 kinds of calendars for different activities:

  • 5 days/week 8h/day calendar
  • 6 days/week 8h/day calendar
  • 7 days/week 8h/day calendar

This programme is 3 years long programme with around 4000 activities, therefore we only want to meassure durations in days.

Knowing the above I have an issue with the lag between activities, since that lag has to be multiplied most of the times by 3 and add weekends, etc, due to the problem of having different calendars for Scheduling relationships Lag (24 Hours calendar) and Activities Calendars (5,6,7 days/week and 8h calendars). As you can see that is a bit of a mess, so what I want to change the Calendar for scheduling Relationships Lag to Predecessor Activity Calendar, but when doing so, it moves most of the programme activities from where they are.

The final question is: Does anyone know any way of solving this issue? Not changing the lag one by one by hand, and also keeping the activities calendars as they are.

 

Thanks a lot in advance,

Luis

6 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    under scheduel thne options

    under scheduel thne options you have the choice a sto which calendar that you want to use for scheduelig relationships.

    you can choose the successors calendar, the predecessors calendar, 24 hour calendar, or the Project Default Calendar. 

    So go to schedule then options then at the bottom choose predecesor calendar

  2. 0
    Luis Garrido ·

    Hi Zoltan,Many thanks for

    Hi Zoltan,

    Many thanks for your answer, but that does not solve the problem, because once I change the calendar for Scheduling Relationships Lag, and reschedule the programme, it will move all my activities. For example, if Activity 1 is linked FS to Activity 2 with 24h lag (1 day with the 24 Hours Calendar), so that activity 2 starts 1 day after activity one finishes, if I change the Calendar for Scheduling Relationships Lag to "predecessor calendar", assuming that Activity one has a 5 days 8h calendar, then, when rescheduling, activity 2 will start 3 days after activity one, or 5 days if there is a weekend in the middle.

     

    Any other solution?

    BR

    Luis

  3. 0
    Zoltan Palffy ·

    of course it will move your

    of course it will move your activities thats the whole point. Your only option then is to adjust each activity duration and lag if any. Good luck 

  4. 0
    Luis Garrido ·

    Thanks Zoltan.

    Thanks Zoltan.

  5. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

  6. 0
    Kannan CP ·

    Luis,As you are using days to

    Luis,

    As you are using days to measure the duration, provide the lag as 1 day instead of 24 hrs. This may solve the problem.

     

    Best Regards

    Kannan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?