Estimate to Complete (ETC) Calculation

Lazy BookwarmMember for 9 years 8 months
Created
6
2
0

Hi,

Estimate to Complete (ETC) values are not changing when I'm changing its calculation criteria under the WBS Earned Value settings. 

Following are the settings of my programme in P6

1) Duration type: Fixed duration and units

2) Percent complete type: Physical

3) Cost is assigned via labour resource.

Please help.

Thanks.

6 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    in the Admin preferences what

    in the Admin preferences what are your settings for Earned Value calculations ?

  2. 0
    Lazy Bookwarm ·

    Technique for computing

    Technique for computing performance % complete: Activity % complete

    Technique for computing Estimate to Complete: ETC= Remaining cost for activity

    Earned Value Calculation: Budgeted values with planned dates

  3. 0
    Zoltan Palffy ·

    change it to budgeted values

    change it to budgeted values with current dates 

  4. 0
    Kannan CP ·

    The actual cost for each

    The actual cost for each activity may be still zero. So the ETC will remains the Budgeted Cost. Or in the WBS, change the setting as ETC=BAC-EV, PF=1.

    Best Regards

    Kannan

  5. 0
    David Kelly ·

    If you report Physical

    If you report Physical percent complete, then what mechanism are you using to reduce the remaining manhours/cost? 

    How are you recording Actual Manhours/Cost?

    Do you have any "Auto Compute" flags set at the Activity or Resource assignment level? 

    How are you determining remaining duration AKA Duration % compete?

    What are the settings in the "Resource Assigments" half of the "Calculations" Tab in the Project Details form?

  6. 0
    Lazy Bookwarm ·

    Hi,Settings under Project

    Hi,

    Settings under Project View->Calculations->Resource Assignments are as follows:

    When updating actual units or cost -> subtract actual from at completion

    "Recalculate actual units and costs when duration % complete changes" and "Link actual and actual this period units and cost" are ticked off. 

    "Update units when costs change on resource assignments" is not ticked off

Log in or join to reply