Assign Budgeted Cost Automatically

Eric EVRARDMember for 19 years 10 months
Created
2
4
0

HI,

I have activities with resources, each Labour resource has its own Price/Unit, Max Units /Time is 100%, I have set Duration Type to Fixed Unit per Time because if I have to change the duration of the Activity I want to change as well the budgeted units.

I would like to automatically link the Budgted cost with budgeted Units as I have the cost per Unit and the Number of Budgeted Unit.

Ex: Duration is 10 days -> Working hours per day is 10 so I enter 100 Budgeted Unit

If I change duration for 12 days, my budgeted units become 120 which is fine, but my budgeted cost is not changing accordingly.

Is there a specific setting to change? I tried a Global Change but for Budgeted Cost it is not proposed

Thank you for your advices

Eric

2 replies

Oldest first
  1. 0
    Eric EVRARD ·

    Hi After some search I found

    Hi After some search I found the tips

    In the resource window in the details tab simply activate the option "Calculate Costs From Units" for each resource or in the Activity Window under Resource Tab add the column "Calculate Costs from Units"

  2. 0
    Zoltan Palffy ·

    that is correct you have to

    that is correct you have to have these checked to do what you want 