Setting Layout

Ranto TumanggerMember for 9 years 7 months
Created
1
1
0

Hi All,

I have problem about layout in primavera, how to setting layout plan value cost, earned value cost  to be percentage in P6.

I have example layout like this. Thank you.

1 reply

Oldest first
  1. 0
    Kannan CP ·

    Hi Ranto,Planned Value Cost

    Hi Ranto,

    Planned Value Cost and Earned Value Cost can be found inside the Earned Value. During update,to get the planned value you need to set the baseline.

    Best Regards

    Kannan

Log in or join to reply