Saving Different Language in P6

Ron LiuMember for 9 years 8 months
Created
1
4
0

Hello everyone,

I have problem saving P6 acitivities that are entered in a different language. I'm using P6 16.1 and my activity description is in Japanese. When I'm done entering the activities and exist the schedule, all activities would display question marks when I open the schedule again.

Does anyone know a fix?

Thank you.

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi RonThis may work in P6 but

    Hi Ron

    This may work in P6 but in Asta I set up a user field then copy paste all the English titles into Google Translate and then copy paste the language back. It is not always accurate but it is quick and simple.

    The problem with Japanes is that there are 3 different texts to the language so the pictoral versions - Katakana & Hiragana may not work. The letter version Kanji may do better.

    Good luck

    Best regards

    Mike Testro