Schedule Filters with WBS or codes Not Transferring
In the Open Standard
Diane ResennaMember for 10 years 7 months
- Created
- 4
- 2
0
Hi all,
I've made several filters within a P6 schedule to show certain WBS sections, and FOW assigned codes.
I know how to save the layout, export layout and import again to transfer filters between schedules. For some reason however, P6 doesn't want to transfer those filters that include the WBS sections or FOW assigned codes. Those parts of the filters show up blank.
Has anyone experienced this or know why P6 behaves this way? It'd be nice not to have to re-do these filters with every schedule update I import.
Thanks!
4 replies
Oldest firstLog in or join to reply