No change in scheudule after "Update Existing" xer import

Wullie HendryMember for 12 years
Created
3
1
0

I update a subcontractors schedule every week and normally everything goes OK.  I have been doing this for over 1 year every week with the same settings and had no problems until around 6 weeks ago.  Now when I import the xer nothing changes, I do not receive any error to notify me and the import appears to be normal until checked.  When I import the xer as a new file I can see the update has been done correctly. 

 

This problems occurs with version 7 "update existing" import.  I have not (nor has he) changed the version etc or any other factor that may affect the import. 

 

Has anyone else encountered this?  I can not figure out why this is happening. 

 

Thanks in advance

 

 

 
 
 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I am confused you say nothing

    I am confused you say nothing changes and then you say the update has been done correctly 

    double check the import settings

  2. 0
    Wullie Hendry ·

    Zoltan As stated the settings

    Zoltan

     

    As stated the settings have been the same for over a week.  

     

    The import does say it has completed and nothing changes hence the reason I have a problem.!

  3. 0
    Zoltan Palffy ·

    check the import settings

    check the import settings change ALL of the setting to insert new

    also if this is on a server make sure that your access rights did not change