Skip to content

Schedule % complete not showing

Adab AzeezMember for 10 years 3 months
Created
9
1
0

GreetingS to All.

in My project most of the WBS do not show schedule % complete, but in that WBS, All activities are showing SChedule% complete as well as Performance % complete ?

What Could be the possible reason ?

Please suggest.

 

Thanks in Advance.

9 replies

Oldest first
  1. 0
    Kannan CP ·

    Is any  budgeted units

    Is any  budgeted units assigned to the activities?

    Regards

    Kannan

  2. 0
    Zoltan Palffy ·

    It will ALWAYS be calculated

    It will ALWAYS be calculated as (BCWS• 100) / BAC

    (budgeted cost for work scheduled times 100) divided by Budget at Completion

    if you do not have cost in your schedule then 0 divided by anything is 0

  3. 0
    Kannan CP ·

    Zoltan,I believe it also

    Zoltan,

    I believe it also depends on the time frame.

    Regards

    Kannan

  4. 0
    Zoltan Palffy ·

    nope just what I wrote

    nope just what I wrote 

  5. 0
    Kannan CP ·

    If you assign a baseline to

    If you assign a baseline to the project, the schedule % may show 100% to an activity , due to the delay of that activity.

  6. 0
    Kannan CP ·

    How the schedule% is

    How the schedule% is calculated for the activities without any cost.

  7. 0
    David Kelly ·

    Adab,To find out how schedule

    Adab,

    To find out how schedule % complete is calculated, show the Schedule % complete value in the columns area, and then under the "view" main menu option in the Windows client, select "hint help".

    Now when you hover over any column heading, it will display how the column is calculated....

  8. 0
    Adab Azeez ·

    With Respect,Thanks Zoltan

    With Respect,Thanks Zoltan Palffy and Kannan CP.

     

    Some of the activities which do not have budgeted cost, still showing SChedule % complete. 

     

     

  9. 0
    Zoltan Palffy ·

    schedule % complete is based

    schedule % complete is based on work not costs. The schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computation is based on where the current data date falls between the activity's baseline start and finish dates.  The Schedule% Complete indicates how much of the activity duration should be currently completed.

    once again you are mixing apples and oranges this has NOTHING I repeat NOTHING to do with costs

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?