Problem in WBS when creating reflection

Ron LiuMember for 9 years 8 months
Created
2
4
0

Hi everyone,

Whenever I create a reflection of a schedule, all the WBS names inside that schedule will also include the word "Reflection". It is very time consuming to delete the word "Reflection" one by one. Has anyone encounter this issue or have a solution for it? 

I'm using R15.2.13

Thank you

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    that is by design

    that is by design 

  2. 0
    Rungsarit Prombrasith ·

    I think you can use Ctrl+R to

    I think you can use Ctrl+R to automatically change the words. Mine is V7 which can use this option.