P6 did no automatic re-calculate Date when update schedule
- Created
- 5
- 3
Dear all,
I'm newbie in group. I have a problem when update Schedule in Primavera as below. Hope get your clarification, instruction:
* When i update activity in P6 by manual follow these steps:
- Step 1: Create Baseline
- Step 2: Update activity (Depending on report, I updated each activity), i met problem, example with Activity A:
+ In Status Tab (Belong to Activity Detail option): Check started (Actual Started Date = Baseline + 2 days)
--> In right way, Actual Finished Date would be recalculated (Actual Finished Date = Actual Started Date + Duration) before I update Physical % complete and Exp Finish (or Remaining duration). But it did not work, I wondering I forgot or missed some option for this action.
Thanks!
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?