Skip to content

Assigning Updated Schedule (Has actuals) as Baseline

Asokan RamamoorthyMember for 14 years 6 months
Created
0
3
0

Dears,

I have a issue while assigning the current schedule as baseline which has actuals already.

I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.

But for all in progress activities i have an issue.Schedule % is not matching with the performance %. Could any one suggest solution on this regards please.

 

Not Activity % completion type is :Physical % Completion

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?