Assigning Updated Schedule (Has actuals) as Baseline

Asokan RamamoorthyMember for 14 years 6 months
Created
1
2
0

Dears,

I have a issue while assigning the current schedule as baseline which has actuals already.

I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.

But for all in progress activities i have an issue.Schedule % is not matching with the performance %. Could any one suggest solution on this regards please.

 

Not Activity % completion type is :Physical % Completion

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    run a global change where

    run a global change 

    where physical % complete is greather than 0

    then duration % complete = physcial % complete

Log in or join to reply