Resource assignment fields grayed out - Primavera P6 16.2
- Created
- 7
- 3
Hi guys, this is my first post here.
I am using Primavera P6 16.2 for my MSc thesis. Current problem that I have is that I cannot assign material resource for specific day of the activity, the fields are gray instead of white, as in few YouTube videos I watched - In this case, I want to assign Concrete for the last day of the activity, and Reinforcment for the first day of the activity. I've tried to change max Units, and tried to change something in Resource settings, but with no success.
And one more question, is it possible to assign same resource to multiple activites with the same quantities?
Kind regards,
Danilo
Screenshot down below
7 replies