Group Interval

Paul KralMember for 9 years 2 months
Created
3
24
0

Hello,

Can anyone tell me whether the date notation - in grouping bands - can be changed to European date format?

I've grouped my layout on 'Start' and defined the Group Interval as Day.

The Grouping bands present the date in following format: "Ddd MM/DD".

Whereas my User Preferences have a different format (also visibile in Start and Finish columns).

Can the date format in Grouping Interval be changed, and if so, kindly share how.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I think that the best that

    I think that the best that you can do is to group by 

    group by           interval

    start                  Year

    start                   month

    start                   day

  2. 0
    Paul Kral ·

    Dear Zoltan,Thanks for the

    Dear Zoltan,

    Thanks for the suggestion however that's not an answer to my question. Neither does is solve date formatting. I suspect the date format in grouping interval is hard coded - I'm looking for someone to disprove or confirm my suspicion.

    Grouping as suggested wil include the year but still the date format remains MM/DD

  3. 0
    Zoltan Palffy ·

    dont think that you can

    dont think that you can change this 