Schedule% complete & Performance % complete is not appearing

Adab AzeezMember for 10 years 3 months
Created
3
1
0
Greetings to all. I am updating a project in primavera.I need to present schedule % and performance % in the WBS of activities. But it is always showing zero, though the activity sch.% and performance% are rolling up with the update. Need a guidance. Thanks in advance.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    create an activity for that

    create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.

  2. 0
    Adab Azeez ·

    Thank you Mr. Zoltan. If

    Thank you Mr. Zoltan. If resource unit per price is not zero then % progress will roll up with every status update. I have done it.
  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 