Primavera P6 Schedule Progression and Duration Type

Emily FosterMember for 15 years 2 months
Created
1
3
0

Here's a look at why it is important to set the duration type to fixed duration and units before beginning to progress the schedule in Primavera P6 http://ed.gr/h5p6

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    or fixed duration and

    or fixed duration and units/time becasue if you do not and then add resouces then your mahours that you put in for the resource will determine the duration of the activity. 