Primavera Timephased Report
In the Open Standard
Jenise SnyderMember for 8 years 9 months
- Created
- 3
- 1
0
I am looking for a way to create a timephased labor report from my current working schedule. I can run one showing budgeted units planned per month by person. Many activities on my current schedule have been delayed/slipped and I would like to have a report showing the new untis planned per month as a result of the slip. All my activities are Physical % Complete and task dependent. I do not track actuals in Primavera.
3 replies
Oldest firstLog in or join to reply