Help!!! Duplicated Resources was not updated by using Baseline update utility in P6 8.2
- Created
- 2
- 5
Hi All,
I had a problem with baseline update in P6.
I am one activity in current schedule with the same resource assigned several times and Zero out some existing resources. I tried to update the baseline for this activity with changed resources. However, after updating the baseline using the following setting:
The baseline budget is not updated properly and I saw that the existing duplicated resources in the baseline was only one of them left. This update actually removed the duplication. This is not what I wanted.
I would be very appreciated if someone have any solutions if anyone have suggestions?
Thanks for your help and I look forward to hearing from you.
David Cui
2 replies
Oldest firstLog in or join to reply