Skip to content

Help!!! Duplicated Resources was not updated by using Baseline update utility in P6 8.2

David CuiMember for 11 years 4 months
Created
2
5
0

Hi All,

I had a problem with baseline update in P6.

I am one activity in current schedule with the same resource assigned several times and Zero out some existing resources. I tried to update the baseline for this activity with changed resources. However, after updating the baseline using the following setting:

 

The baseline budget is not updated properly and I saw that the existing duplicated resources in the baseline was only one of them left. This update actually removed the duplication. This is not what I wanted.

I would be very appreciated if someone have any solutions if anyone have suggestions?

Thanks for your help and I look forward to hearing from you.

David Cui

2 replies

Oldest first
  1. 0
    David Kelly ·

    I know everything about

    I know everything about this.  Baseline Update has never worked, still has issues in version 17.12, but the issues change with each version. I still have a guide for doing this with version 8.3.  Send me your contact details and I will send you the PDF file....

  2. 0
    Zoltan Palffy ·

    David Kelly I would also like

    David Kelly I would also like to see your solution

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?