Baseline versus Actual Schedule Duration Complete Comparison

Gulsah ErincMember for 8 years 6 months
Created
3
2
0

Hello,

I need to compare Baseline Duration %Complete versus Actual Duration % Complete. I know that I can see this with "Schedule % Complete" column at activity level, not WBS Level. Schedule % Complete uses EV data for WBS. But what I need is to compare duration COmplete at WBS level.  In order to do it, I created a dummy "duration" resource for each activity. Each activity's original duration is equal to its resources. I use this data when I export it to excel, not in primavera. Is there a way that I can creaye uSer defined column or etc. to calculate Baseline Planned Duration COmplete at WBS level?

Thank you.

Gulsah Erinc 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    why not use the existing

    why not use the existing field BL Project Duration and roll it up by wbs

  2. 0
    Gulsah Erinc ·

    Thank you Zolfan; but what I

    Thank you Zolfan; but what I am trying to figure out is something else. I will try to explain with an example. I have a schedule with 5 activities eact having "original duration" equal to 20. Total sum of activity durations is 5x20=100days. 

    Lets say 20 days later only one activity should finish. It means that my activity duration progress is 20/100=20%. But in actual situtation, only one acticity is progressed by %50, which means 10days. My actual activity duration progress is 10%. 

    How can I show these 10% and 20%s at WBS Summary level?

    Thanks,

    Gulsah 

  3. 0
    Zoltan Palffy ·

    try using activity % complete

    try using activity % complete and rolliing up the WBS