P6 SCHEDULE PROBLEM!!!
In the Open Standard
Emrah KayaMember for 8 years 5 months
- Created
- 1
- 2
0
Hi guys,
I have a problem with my p6.I am done with my planning and I want to put my new data for the next month manually;
*First problem=When I click the start box in status bar and change the data with a different date finish box doesn't change automatically.
*Second problem=When I change for example my first activity dates and there is a lag time. And I click the F9 , put my new data date and start to schedule the data date I put became the next activity start date. Let me explain this way also
Activity (A) Start date:03/05/2018-end date 10/05/2018
Activity (B) Start date 11/06/2018-end date 23/05/2018
Changing activity (A) and --> start date 05/05/2018 end data 12/05/2018
Click the schedule and put data date as 1 June start schedule
Activity (B) becomes start date 1/6/2018-end date 13/6/2018
Thank your help from now. And sorry I kept it long to write I am new on P6 and doing my thesis..
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?