Database Cleanup - SQLlite - R8.4

Andrew SargentMember for 11 years 8 months
Created
2
2
0

After reaching the 4GB limit on the XE database for the 1000th time I decided to just switch over to SQLlite. I have no reached the point where even my SQLlite database is bloated with POBS and old codes. Can someone tell me how to cleanup my sqllite DB? 

2 replies

Oldest first
  1. 0
    David Kelly ·

    SQLite Management Studio.

    SQLite Management Studio. Don't leave home without it.

  2. 0
    Zoltan Palffy ·

    there are several thing that

    there are several thing that you can do

    1. Clean the POBS tables in the existing database here is how

    Click on start All Programs, Microsoft SQl Server 2005, SLQ Server Management Studio

    Authentication: Should be SQL Server Authentication

    Login: sa

    Password: Prima123Vera

    Then click connect

    Expand the database folder and click on pmdb$primavera

    Then up top select new query

    Then type this

    delete POBS;

    the right click and select execute

    now you can close and exit out of sql

    2. download this POBS cleaner adn clean every XER file prior to imporing it

    http://scheduleanalyzer.com/PurgePOBS.exe

    3. You can exort the old projects as xer files save them to a thumb drive, an external hard drive or a network drive then delete these old projects.

    4. You can create another database and stsrt to add NEW projects to that database 

     

Log in or join to reply