Budget at completion, Earned value cost, Planned value cost is double of what is mentioned in the resources

Gowhar MirMember for 8 years 5 months
Created
3
4
0

Hi there.

I am working on a project and I used the columns Budget at completion, Earned value cost, Planned value cost and suddenly they are showing exactly twice the data that is there in the resources tab. Any solution?

 

Thanks

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1st ALWAYS ALWAYS go to the

    1st ALWAYS ALWAYS 

    go to the projects directory 

    makes ure that your project is highlighted

    click on the resources tab 

    on the lower right under resource assignments make sure that 

    RESOURCES and be assigned to the same activity more than once is NOT checked 

    this will eliminated double dipping the resource or adding it again if your re-import an excel file 

  2. 0
    Gowhar Mir ·

    Thanks for the reply, Zoltan.

    Thanks for the reply, Zoltan. I checked the prog, no double resoucing was done but what had happened is that there was budgeted cost assigned in resource tab and also in expense tab so the two were doubling up to display the budget at completion. I removed the budgetd cost from expense tab now to keep it just as the non-labour resource.

  3. 0
    Zoltan Palffy ·

    I never ever use expenses

    I never ever use expenses glad you figured it out