Updating the baseline
In the Open Standard
Gowhar MirMember for 8 years 5 months
- Created
- 6
- 1
0
Hi there! I wanted to know if there is a process to update the baseline or the current program by making changes in either of them. For example, if I have made changes in my baseline few months after the commencement of the project, is there a way from which I can copy this update into the current program or vice versa? Say I needed to add some activities to the project, change duration of few activities. Is there any way with which I can incorporate only these changes in the program?
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?