Skip to content

Manpower Budgeted Time is Changing

Suhaib NassarMember for 8 years 3 months
Created
3
1
0

Dear all,

The manpower budgeted time of most of the activities keep changing over and over which also change the overall budgeted time in the resource assignment. Is there any ability to make them fixed as I built them in the beginning of the project?

Suhaib

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    change duration type to fixed

    change duration type to fixed duration and units/time 

  2. 0
    Suhaib Nassar ·

    Many thanks Mr. Zoltan

    Many thanks Mr. Zoltan

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?