Units discrepancy for s-curve

Morne Johann BeeslaarMember for 10 years 7 months
Created
4
2
0

Loaded my permitting with units to track an s-curve. Assigned 200 000 units across the activities. My report only has 194104 units in cumulative planned but cumulative estimate to & at completion indicates the 200 000 units loaded. No filters assigned that can trip me up and percent complete type set to units.

 

What could be the problem?

 

Running 18.8

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    make sure your filter is set

    make sure your filter is set to ALL activities 

  2. 0
    David Kelly ·

    Primavera holds the numbers

    Primavera holds the numbers in two places, and they do get out of synchronisation.

    You should check the units in both the “Activities” window and the “Resource assignment” windows

    When you do a resource  profile/spreadsheet, the numbers come from one table, the Activity spreadsheet/profile and ALL earned value data comes from the other.

  3. 0
    Morne Johann Beeslaar ·

    Thanks David, found it is

    Thanks David, found it is exactly the problem.

     

    Going to delete resources and reload as I guess this is the only fix.

  4. 0
    Zoltan Palffy ·

    under edit user

    under edit user preference

    turn your decimal places on 

    Time units tab