Units discrepancy for s-curve
In the Open Standard
Morne Johann BeeslaarMember for 10 years 7 months
- Created
- 4
- 2
0
Loaded my permitting with units to track an s-curve. Assigned 200 000 units across the activities. My report only has 194104 units in cumulative planned but cumulative estimate to & at completion indicates the 200 000 units loaded. No filters assigned that can trip me up and percent complete type set to units.
What could be the problem?
Running 18.8
4 replies