Skip to content

Detaching the baseline

Adab AzeezMember for 10 years 3 months
Created
7
4
0
Greetings to everyone. I have to detach the baseline to modify some duration and some calenders. After modification I am expected to re assign the same base line. Any Suggestion , what precaution should I take during this...? Thanks in Advance.

7 replies

Oldest first
  1. 0
    Anoon Iimos ·

    Is there a problem with

    Is there a problem with removing or detaching your baseline and do the editing as a stand-alone schedule, and then assign it back to your current or working schedule whenever you want? Well, I guess you need to make sure first that your baseline is the exact copy of your current schedule whenever you attach or detach it. Exact copy means: exact number of activities and descriptions. Of course other details may vary depending on how your plan is progressing actually.
  2. 0
    Kannan CP ·

    Hi Abad,If the changes are

    Hi Abad,

    If the changes are only in baseline and not in current Program, probably you would be comparing Programs with different logic, duration, productivity resources etc.

    BR

    Kannan

  3. 0
    Zoltan Palffy ·

    reverse the way that you

    reverse the way that you attached it 

    select project

    then assign baseline

    then under Project Baseline select <Current Project> as the baseline

    als under User Baseline

    Primary select <Current Project> as the baseline

    select OK

    next under project select Maintain Baselines

    highlight the scheduel that is listed there and on the rigth select Restore 

  4. 0
    Anoon Iimos ·

    Now this becomes interesting.

    Now this becomes interesting. Adab, comparing baselines and current schedules need to be consistent (consistency is the key). Though of course there will always be some details to vary, as plans don't always turn out exactly the way you planned them. Just be careful with the settings (I mean "Retained Logic" vs. "Progress Override", I guess you already knew how and where to use them?).
  5. 0
    Zoltan Palffy ·

    yes NEVER use progress over

    yes NEVER use progress over ride 

  6. 0
    Anoon Iimos ·

    Adab, Tip: Don't always

    Adab, Tip: Don't always believe in everything you read, especially if the source is unreliable. Nowadays "fake news" are rampant. Beware!
  7. 0
    Zoltan Palffy ·

    I told you how to detach a

    I told you how to detach a schedule nothing fake about that 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?