Level of Effort Activities
In the Open Standard
Mansoor SadiqMember for 10 years 10 months
- Created
- 7
- 2
0
Hi
I added a Level of Effort activity in a WBS, as per its nature it will cover the entire project duration.
Assuming that by assigning a resource this this Level of Effort activity, Project cost (User rate X Activity Duration) should be updated, but the cost of Level of Effort Activity is always Zero.
what I think the poject cost should be updated due to Level of Effort Activity, please comment
regards
Mansoor
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
