EOT
In the Open Standard
Gowhar MirMember for 8 years 5 months
- Created
- 8
- 1
0
Hi there.
We submitted a baseline at the start of the project that was approved and had been following the same for some time. Then we revised the baseline by changing the construction methodology to change the sequence of activities and also the duration of some activities keeping the Project Finish Date same as in the original baseline. Now we need to submit an EOT claim, I want to ask you that should we prepare out EOT based on the original baseline or the revised baseline?
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?