P6 "Ghost" resources - not assigned to WBS/Activity, but exist in Resource Assignments?
In the Open Standard
Marc T2Member for 7 years 8 months
- Created
- 6
- 2
0
Hi All,
wondering if anyone has come across this before and has a solution at all?
I've got a project with circa 250k hours remaining, and on 'Activities' screen all looks ok. When I switch to 'Resource Assignments', grouped by WBS, I have three resources sitting outside the project under 'No WBS' / 'No Activity Name' / Blank Activity ID but with remaining hours meaning the total is different. I'm not able to delete them via this screen either, although I am able to delete others?
any help much appreciated
Many thanks
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?