Not sure if its been covered before but for information

I found I was getting loops in a imported schedule that I was updating in P6 with a schedule from a contractor.  I would only update the activities, relationships, and resources on the activities.   All the rest i would set to keep existing.   The contractor had made a number of logic changes in the plan.   I imported and went to F9 the project after some links to outside milestones and I suddenly had loops appear.   I was thinking that they were in the contractors XER they had submitted.   I tested thiers as a new project and F9 worked fine.

I removed the loops and imported the plan again and got the loops again.    Finally I stopped to read the delete check box in the import modifcation area and I deleted all the relationships in the current plan and replaced the same with the import plan.  I didnt have any more loops 

Just thought maybe you could use this info for those ever running into the same problem.

I think the import plan was simply adding the logic which was new to the logic already there.

2 replies

Oldest first
  1. 0
    Sanjeet Teri ·

    Thanks Ron for Sharing this.

    Thanks Ron for Sharing this.

  2. 0
    Faye Hewitt-Lighty ·

    Thank you for sharing this

    Thank you for sharing this information

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?