Skip to content

Remaining Labor Unit by Week

Jithin KambhikanamMember for 15 years 6 months
Created
3
1
0
Hello Everyone, Need help on how to get a report on Remaining labour units per week after updating the Schedule. Like, Week 24.3 31.3 7.4 Mason 10 5 6 Regards Jithin

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    view show on bottom resource

    view show on bottom resource useage spreadsheet

    on the right modify resource usage profile

    right click spreadsheet fields remaining units

    and make the time scale weeks

    or

    make sure your time scale is weeks

    view show on bottom resource useage profile 

     on the right you rigth click and select resource usage profile options

    on the data tab under display select units

    and under that select remaining early 

    click on the graph tab and at the bottom check calculate average and base on hours per time period

    the divide by interval should be 40 is viewiing for weeks.

     

  2. 0
    Jithin Kambhikanam ·

    Thanks Zoltan,Did that and it

    Thanks Zoltan,

    Did that and it worked. Apart from that I also right clicked on the Resource Spreadsheet and clicked on Spreadsheet Field from which I selected "Remaining Units".

    Regards

    Jithin

  3. 0
    Zoltan Palffy ·

    of course it worked

    of course it worked 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?