Grouping a layout

Ron BeecheyMember for 10 years 6 months
Created
1
2
0

I would like to group my layout on a given level of the wbs and below

So I would like to select level 6 and below and not show the upper levels (1-5).   Is there a method by filtering or selecting that I have missed

1 reply

Oldest first
  1. 0
    Ron Beechey ·

    I have found the method to

    I have found the method to work with the WBS.   In the grouping window select WBS and then turn off Indent and select the level to start on.  If you need a second level add WBS again and select the next level to add to the grouping.

    We created a wbs what made it down to the system level and then the piping line level.   These are the ones I would like to see the tasks grouped and sorted by.  

    This could be good info for all users.  