Baseline
- Created
- 3
- 3
I am using a stand alone version of P6 and have run into an issue with Baselines
I create a baseline for each week to show variance for the work that was planned to be completed that week. I have just recieved a notice that I have reached the max number of Baselines for the project. I deleted a few older ones and then created a new one for the current week. In looking at the variance column for this week I expect to see zero variance and much to my surprise the numbers were from -60days to plus 30 days. there were a few that were zero but not many.
Anyone else had this problem and how did you fix it.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?