Performance % Complete showing 0%

Eric GonzalezMember for 7 years 4 months
Created
3
3
0

I have an EPC resource loaded schedule that is not giving me a performance % complete percentage. All of the activites are "physical" % complete type. However, I only have resource in the engineering side and not in the construction or procurement. What is the purpose for not giving me an accurate % complete? What is the best solution going forward?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    do you have baselin

    do you have baselin attached? 

    if so in the Admin

    Admin Preferences

    Earned value

    Earned Value Calculations

    select Budgeted value with current dates

    FYI

    The Performance % complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule which depends on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of, the activities planned worth has been earned so far.

    Having something quantifiable and measurable is always the best way to measure progress that could be manhours or commodities such as LF of conduit ect.

    Performance Percent Complete for the activity is based on Units Percent Complete. Activities without a Resource curve assigned to one or more of the Resource Assignments will use the Activity percent complete

     

  2. 0
    Eric Gonzalez ·

    Zoltan,  Thanks for the

    Zoltan, 

     

    Thanks for the information. I have assigned the baseline. I have not had this problem before when I've added manhours and resource loaded a schedule. 

  3. 0
    Zoltan Palffy ·

    you have 3 choices to

    you have 3 choices to calculate earned value 

    Budgeted value with planned dates

    At completeion with current dates 

    Budgeted value with current dates

Log in or join to reply