NAN & INF

Warren SikaMember for 13 years 8 months
Created
3
4
0

Hello everyone.

I have problem with getting a NAN and INF in my Revised Baseline.

Scenario is this:

1. Baseline has actuals and loaded with Resources

Prior to getting the NAN (Total Float) and INF (Original Duration), all resource curve are in dafault but when I change some Resource Curve (i.e. Front Loaded), I get this NAN and INF.

Does anyone know how to solve it? Is changing the resource curve will cause this?

  

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    change the duration type to

    change the duration type to fixed duration & units/time. You can add a column for duration type do the first one then doa fill down

    also in the PROJECTS directory under the Resources tab uncheck drive activity dates by default

  2. 0
    Warren Sika ·

    Thank you Engr. Zoltan.

    Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time).  Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.

  3. 0
    Zoltan Palffy ·

    WRONG 100% WRONG !budgeted

    WRONG 100% WRONG !

    budgeted units will NOT chnage if duration is changed (if i change to fixed duration & units/time).  

    hence the word FIXED DURATION & UNITS/time