S Curve Manhour- Baseline , Actual , Forecast

Jithin KambhikanamMember for 15 years 6 months
Created
5
3
0

Hello Everyone,

 

I would like to make a S Curve in Primavera which shows Planned, Actual and Forecast S Curve.

The basis of S Curve to be manhours / Week.

Can S Curve in Primavera show % Planned per week as Lables like in Excel.

I want to calculate the S Curve which shows end of the Week Palnned % and Actuals (Not start)

Please guide me.

 

Regards

Jithin

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    create a resourceassign the

    create a resource

    assign the resource to the activities

    assign the proper manhours to each activity

    view show on bottom resource usage profile

    select the cureves that you want to show

  2. 0
    Jithin Kambhikanam ·

    Hi Zoltan, I am looking for a

    Hi Zoltan,

     

    I am looking for a s curve which would be like this showing lables.

     

  3. 0
    Zoltan Palffy ·

    create a resourceassign the

    create a resource

    assign the resource to the activities

    assign the proper manhours to each activity

    view show on bottom resource usage spreadsheet

  4. 0
    Jithin Kambhikanam ·

    Hi Zoltan,But that doesnt

    Hi Zoltan,

    But that doesnt show % Planned Label per Week. 

     

    It shows the curve but doesnt show the label.

    Regards

    Jitin 

  5. 0
    Zoltan Palffy ·

    NOTHING show the label you

    NOTHING show the label you did not ask for the label 

Log in or join to reply