Purpose of Retired activities in Schedule

Nathan SivaMember for 12 years 5 months
Created
3
2
0

Hi Expats,

In one of my UK clients schedule, they advised  to retire completed activites and non performing activites in the schedule. and my collegues recommended to change the duration of non performed activities duration to 1D in the schedule to avoid those activities in critical path.

Can you please explain the purpose of retiring the activities in the schedule?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    an actviity can be in one of

    an actviity can be in one of 4 categories

    not started

    in progress 

    completed

    modified in progress using suspend and resume

    whne you say retire completed I do not know what you mean ? I also do not know what a non performed actviities are

    if you mean the activities are no longer in the scope then I would should show the same actual start and finish date equal to the date that you were told that this activity is not longer in the scope. 

    PUtting 1 day duration WILL make them critical making them complted will not

    I would also assign an activity code theses and make a comment in the notes tab. This way you can filter and gropu these if need be. 

  2. 0
    Nathan Siva ·

    Thanks for the detailed

    Thanks for the detailed explanation Zoltan. it  makes sense.

  3. 0
    Zoltan Palffy ·

    Glad I could help

    Glad I could help 