Calendar Days do not match Calendar Hours?

Rodney JonesMember for 14 years 4 months
Created
3
2
0

Hi,

 

I have a calendar running 10 hours per day, 5 days per week. It is assigned as the Activity default calendar. When I create a new activity with a duration of 3 days and then change my User Preference to show Duration in Hours, the hours are only 24 but I expected them to be 30.

 

Why is this happenning? 3 days on a 10 hour per day calendar should be 30 hours but it appears to be referencing an 8 hour day.

 

You help would be greatly appreciated.

 

Rod

3 replies

Oldest first
  1. 0
    David Kelly ·

    Modify your calendar, and

    Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days
  2. 0
    Zoltan Palffy ·

    you have not set the hours

    you have not set the hours correctly or have not set the correct default calendar  

  3. 0
    Rodney Jones ·

    Brilliant, Yes, it was the

    Brilliant, Yes, it was the Timeperiods.

     

    Thanks.

     

    Rod