Importing excel dates- changing the 00:00 to 17:00
- Created
- 4
- 3
Importing excel dates- changing the 00:00 to 17:00 . The odd thing is when you look at the excel "bar" it shows 5/16/2018 12:00:00. I have had schedule effected by the "hours" so i want it 5pm or 17:00. I tried replace but there was no excel option with the date and time and am/pm. I am not a big fan of the way P6 "always secretly includes hours", seems like P3 was easier. I was watching a planacademy video about it and sometimes he changed the time and sometimes he did not - strange. I have given up changing it automatically with replace all in excel, maybe I will have to change all in P6 - we will see.
4 replies
Oldest firstLog in or join to reply