Problem of Too many FS Relations

Rauf KensukMember for 6 years 9 months
Created
0
2
0
Project: Typical Residence House Project
 
I am preparing a schedule of residence project. Construction contains 17 Blocks and each block has approx. 11 floors. So that too many activities and it s about to get 11.000 activites. 
 
Even i don't want but i use too many "FS relationships" in order to hang the activities in timeline and I know it will cause too many Out-Of-Seqeunce ("OOS"). 
 
1st Floor >>FS>> 2nd Floor >>FS>> 3rd Floor
 
In practical 2nd floor may start without waiting for finishing 1st Floor and that cause "OOS"
 
To avoid that i m thinking to use 1st Floor >>SS and FF and + LAG: 1st Floor Duration >> 2nd Floor. If 2nd floor starts before finishing 1 st Floor, it will cause a gap as 1st Floor Remaining duration for 2nd Floor activity but not OOS, I think. 
 
Doing SS + FF + Lag, what else may it cause a problem that I can't imagine ?

Thanks in advance

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?